    BALLOKI 225 CCPP and MURIDKE 234 CCPP steam power plant, Pakistan

    Implementation Date

    2010

    Field

    Gas

    Challenge

    In 2009 and 2010, we carried out our first and an very large order in Asia at the outset. We ensured the delivery, installation, supervision and commissioning for two Pakistani steam-gas power plants.

    Solution

    Balloki

    • EDS inlet closure.
    • Safety shut valves.
    • Two filtration and measuring sets for a flow rate of 56,000 m3/hour.
    • Preheating of gas using 800 kW hot water exchangers.
    • 1.2 MW gas boiler room for preheating of gas in a container design.
    • Compressor station with three CAMERON compressors, including compressed air, nitrogen and cooling system.
    • Gas regulation station for boiler room RS 1200/2/2-440.

    Muridke

    • EDS inlet closure.
    • Safety shut valves.
    • Two filtration and measuring sets for a flow rate of 56,000 m3/hour.
    • Preheating of gas using 800 kW hot water exchangers.
    • 1.2 MW gas boiler room for preheating of gas in a container design.
    • Gas regulation station for boiler room RS 1200/2/2-440.

    Parameters

    Balkoki

    Qmax = 56 000 m3(N)/hour
    Inlet pressure: 25–45 bar
    Outlet pressure: 23–28 bar
    Outlet temperature: 30 °C

    Muridke

    Qmax = 56 000 m3(N)/hour
    Inlet pressure: 28–40 bar
    Outlet pressure: 28 bar